Building Permit
Learn how to obtain a building permit in Poland. Find out whether you need a permit or a notification suffices, what documents to prepare, how to submit an application at the starostwo and how long the procedure takes — step by step.
Variants
Building permit (full procedure)
You are building a house over 70 m², a multi-family building, a commercial facility or another structure requiring a permit
Construction notification (simplified procedure)
You are building a detached single-family house up to 70 m², a free-standing outbuilding or another structure subject to notification
Legalization of unauthorized construction
You built a structure without the required permit or notification and want to legalize it
How to handle it — step by step
Before starting construction you must establish what development conditions apply to your plot.
Local spatial development plan (MPZP)
The MPZP is a document adopted by the municipal council that defines:
- Land use (residential, commercial, agricultural, etc.)
- Permitted building height
- Maximum built-up area
- Building lines (minimum distances from plot boundaries)
- Required number of parking spaces
How to check the MPZP?
- Visit the BIP website of your municipality and look for the Spatial Planning section
- Check the geoportal.gov.pl service — some municipalities publish the MPZP online
- Submit an application for a MPZP extract and map excerpt at the municipal office
No MPZP — development conditions (WZ)
If the plot is not covered by the MPZP, you must obtain a development conditions decision (WZ):
- Submit a WZ application at the municipal office
- Attach a base map with the planned investment marked
- The office will issue a decision within 90 days (indicative deadline)
Fee for MPZP extract
- Extract: from 30 PLN (up to 5 pages) to 50 PLN (over 5 pages)
- Map excerpt: 20 PLN per A4 page (max 200 PLN)
Documents
- Application for MPZP extract and map excerptOptionalIf the plot is covered by the MPZP — submitted at the municipal office
- Application for development conditions (WZ)OptionalIf the plot is NOT covered by the MPZP — submitted at the municipal office
- Base map at scale 1:500 or 1:1000RequiredFor WZ application — ordered from the district geodesy department
Fees
| Payment method | Fee |
|---|---|
bank transfer Exemptions: Stamp duty for WZ decision; free for single-family houses for own use | 107,00 PLN |
The construction project must be prepared by a person holding building design qualifications in the relevant specialty.
A construction project consists of:
- Site development plan — positioning of the building on the plot, access roads, utilities, greenery
- Architectural and construction design — floor plans, cross-sections, elevations, technical description
- Technical design — structure, installations (plumbing, electrical, heating, ventilation)
Ready-made vs. individual design
- Ready-made (typical) design: cheaper (3,000–10,000 PLN), faster, requires adaptation to the plot
- Individual design: more expensive (15,000–50,000+ PLN), longer preparation time, fully customised
Adaptation of a ready-made design
A ready-made design must be adapted to the specific plot by a licensed architect. Adaptation includes:
- Adjustment to MPZP/WZ
- Adjustment to soil conditions
- Positioning on the plot
- Any changes (within those permitted by the author)
Time
Individual design: 2–6 months. Adaptation of ready-made: 2–8 weeks.
Documents
- Map for design purposesRequiredOrdered from a licensed surveyor — cost approx. 1,500–3,000 PLN, time approx. 2–4 weeks
- MPZP extract and map excerpt or WZ decisionRequiredThe architect needs them to design a building compliant with regulations
- Utility connection conditionsRequiredObtain from suppliers: electricity, gas, water and sewage
- Geotechnical soil surveyOptionalRecommended — the architect needs it to design the foundations
Before submitting the building permit application (or notification), gather the full set of required documents.
Documents for a building permit
- Building permit application (form PB-1)
- Site development plan — 3 copies
- Architectural and construction design — 3 copies
- Declaration on the right to dispose of the property for construction purposes (form PB-5)
- Development conditions decision (if no MPZP)
- Utility connection conditions (electricity, gas, water, sewage)
- Any agreements and opinions (heritage conservator, road manager, etc.)
Documents for construction notification (house up to 70 m²)
- Construction notification (form PB-2a)
- Site development plan — 3 copies
- Architectural and construction design — 3 copies
- Declaration on the right to dispose of the property (PB-5)
- Declaration that the house is for own use (for houses up to 70 m²)
Technical design
The technical design is not attached to the application — you submit it to the construction manager before works begin.
Documents
- Form PB-1 (permit) or PB-2a (notification)RequiredOfficial form available on gov.pl or at the starostwo
- Site development plan (3 copies)RequiredPrepared by a licensed architect
- Architectural and construction design (3 copies)RequiredPrepared by a licensed architect
- Declaration on the right to dispose of the property (PB-5)RequiredYou confirm that you are the owner or have the owner's consent
- Development conditions decision (WZ)OptionalRequired only if there is no MPZP
The building permit application (or construction notification) is submitted to the starostwo powiatowe (or city office with district rights) competent for the location of the plot.
Submission methods
- In person at the starostwo registry
- By post — registered letter
- Electronically — via the e-Budownictwo portal (requires a Trusted Profile)
e-Budownictwo portal
The e-Budownictwo portal allows online submission:
- Log in via login.gov.pl
- Complete form PB-1 or PB-2a
- Attach the project electronically (PDF)
- Sign with a Trusted Profile and submit
Stamp duty
- Building permit for a single-family house: exempt from duty
- Building permit for a commercial building: 1 PLN per m² of usable area (max 539 PLN)
- Construction notification: free of charge
Processing time
- Building permit: the authority has 65 days to issue a decision (from the day a complete application is submitted)
- Notification: the authority has 21 days to raise an objection; no objection = tacit consent
Documents
- Full set of documents from the previous stepRequiredForm PB-1/PB-2a + design + declarations + agreements
- Proof of stamp duty payment (if required)OptionalSingle-family houses and notifications are exempt from duty
Fees
| Payment method | Fee |
|---|---|
bank transfer Exemptions: Free for single-family houses; commercial buildings: 1 PLN/m² (max 539 PLN) | 0,00 PLN |
After submitting a complete application, the authority processes it within the statutory deadline.
Deadlines
- Building permit: up to 65 days from submission of a complete application
- Construction notification: 21 days for tacit consent (no objection = you can build)
What happens during processing?
- The authority checks the completeness of the application (deficiencies → summons for supplementation)
- The authority verifies the design for compliance with MPZP/WZ and building regulations
- The authority notifies the parties to the proceedings (neighbours may submit comments)
- The authority issues a building permit decision (or refuses)
Coming into force
The decision becomes final after 14 days of delivery, if none of the parties appeal. Only after it becomes final may you start construction.
Appeal
Against a refusal decision (or against a permit decision — by neighbours), an appeal to the voivode is available within 14 days of delivery.
Validity of the permit
The building permit expires if construction is not started within 3 years of the decision becoming final or is interrupted for more than 3 years.
Documents
- Building permit decisionRequiredCollected at the starostwo or received by post/through e-Budownictwo
After receiving a final building permit (or tacit consent on a notification) you may start construction.
Before starting
- Hire a construction site manager — a person with building qualifications to manage the works
- Obtain a construction log — since 2023 an electronic construction log (EDB) is mandatory, available on e-Budownictwo
- Hand the technical design to the site manager — it must be available on the construction site
- Notify of the intention to start works to the building supervision authority (at least 7 days before starting)
Electronic construction log (EDB)
Since 2023, the construction log is kept electronically:
- Log in to e-Budownictwo
- Submit an application for a construction log
- Provide the building permit number
- The site manager keeps the log — making entries electronically
Information board
Place an information board on the construction site containing:
- Type of works and address
- Building permit number
- Investor's and site manager's details
Important
Construction is carried out in accordance with the approved design. Significant deviations require a change of building permit.
Documents
- Final building permit or notification confirmationRequiredMust be final (14 days from delivery without appeal)
- Electronic construction log (EDB)RequiredApplied for on e-Budownictwo.gunb.gov.pl
- Technical designRequiredMust be available on the construction site
- Notification of intention to start construction worksRequiredSubmitted to the building supervision authority at least 7 days before starting
If you built a structure without the required permit or notification, you can legalize it at the district building supervision inspectorate (PINB).
Simplified procedure (structures older than 20 years)
Since 2020, structures built without a permit more than 20 years ago can be legalized in a simplified procedure:
- Submit a legalization application to PINB
- Attach: declaration on the right to property, post-completion geodetic inventory, technical expert opinion
- No legalization fee
- PINB issues a legalization decision
Standard procedure (newer structures)
For newer unauthorized constructions:
- PINB issues a ruling to stop the works
- Orders submission of documents (substitute design, certificate of compliance with MPZP)
- After document submission — charges a legalization fee (multiple of the rate 500 PLN × coefficient)
- After payment — issues a legalization decision
Legalization fee
The fee depends on the type and size of the structure. For a single-family house it may be 50,000 PLN. Non-payment = demolition order.
Documents
- Legalization applicationRequiredSubmitted at the district building supervision inspectorate (PINB)
- Declaration on the right to dispose of the propertyRequiredForm PB-5
- Post-completion geodetic inventoryRequiredOrdered from a licensed surveyor
- Technical expert opinionRequiredConfirming that the structure is safe for use
Fees
| Payment method | Fee |
|---|---|
bank transfer Exemptions: Free simplified legalization (structures 20+ years old); standard legalization fee: depends on structure (single-family house: approx. 50,000 PLN) | 0,00 PLN |
After completion
The site manager must keep the electronic construction log with current entries. This is necessary for the final inspection.
More informationDuring construction, order utility connections: water, sewage, electricity, gas. Lead times may be several months.
After completing construction, submit a notification to PINB or an application for a use permit (depending on the type of structure). Attach the construction log, geodetic inventory and site manager's declaration.
More information